Previous Topic

Next Topic

Book Contents

Book Index

Completing an Item Transfer

The procedure for completing an Item Transfer is as follows:

  1. Add [INS].
  2. Create Transfer. Enter a reference number for the transfer.
  3. Description. Enter a further description if required.
  4. Save [F9].
  5. From Location/To Location. Use the down arrow to select correct locations.
  6. Date. Will default to current date. To change the day use the [up/down arrow keys]. To change the month, use the [up/down arrow keys + shift key].
  7. Enter the following details:

    CS Screenshot - linked

  8. Process [F9], and select from the following options:

See Also

Item Transfer <IT>

Editing an Item Transfer